PROJECT STATUS REPORT

 

2020 Sanitary Sewer Rehabilitation Project

Work began week of September 14, 2020. City sent out general information letters to affected residents along with telephone contacts to answer questions and/or concerns. Contractor also handing out contact information (door hangers) to residents with advance notice including dates and times to limit sanitary use. Sewer lining phase is 95% complete-Contractor performing finish work on remaining segments. The Manhole Rehabilitation phase (manhole lining and chimney replacement) is scheduled to begin April and will be completed May, 2021. Final completion date is May 28, 2021.

 

2021 N Gould Street Project

  1. N Gould Street from Oliver to Moore: Work scope includes pavement rehabilitation with select curb and gutter repair, ADA sidewalk ramps, select sidewalk repair, complete storm sewer replacement, and permanent pavement markings and signing.  No water main to be installed.  Project is a MDOT Small Urban Program project.  Project has been awarded to Crawford Contracting.  Anticipated start date is June 14, 2021.  Preconstruction meeting will be held April, 2021.

 

2021 Street Program – Contract 1 (Crush and Shape)

  1. Glenwood Avenue from south end to Farr: Work scope includes widening existing road, pulverizing with stabilization, and asphalt resurfacing.  Project under design phase.

  2. Garfield Avenue from south end to Corunna: Work scope includes widening existing road, pulverizing with stabilization, and asphalt resurfacing.  Project under design phase.

  3. Lincoln Avenue from Farr to Monroe: Work scope includes widening existing road, pulverizing with stabilization, and asphalt resurfacing.  Project under design phase.

  4. McMillan Avenue from south end to Industrial: Work scope includes widening existing road, pulverizing with stabilization, and asphalt resurfacing.  Project under design phase.

  5. Park Street from Harper to Ridge: Work scope includes widening existing road, pulverizing with stabilization, and asphalt resurfacing.  Project under design phase.

  6. Pearce Street from South to Francis: Work scope includes widening existing road, pulverizing with stabilization, and asphalt resurfacing.  Project under design phase. 

  7. South Street from McMillan to Aiken: Work scope includes widening existing road, pulverizing with stabilization, and asphalt resurfacing.  Project under design phase.

 

2021 Chip Seal Project – Contract 1 (Double Chip Seal and Fog Seal)

The following streets will be chip sealed:

  1. Auburndale from Broadway to Alger

  2. Carr from South to Herman

  3. George from South to Herman

  4. Glenwood from Farr to Monroe

  5. Herman from Carr to Kenwood

  6. Hiram from George to Chipman

  7. Nelson from South to Herman

  8. South from Chipman to Shiawassee

  9. Washington from south city limits to Gute

  10. Woodlawn from south end to Farr

Project is scheduled to be awarded to Highway Maintenance at the April 5 city council meeting.  Work will begin around May 17, 2021 and be completed by June 30, 2021.


2021 Chip Seal Project – Contract 2 (Double Chip Seal and Fog Seal)

The following streets will be chip sealed:

  1. Adams from King to Elizabeth

  2. Alta Vista from Center to Shady Lane

  3. Alturas from Center to Shady Lane

  4. Chestnut from Stewart to Main

  5. Chipman Lane from Chipman to dead end

  6. Corlett from south end to Marion

  7. Jennett from Adams to Washington

  8. Mack from Robbins to Chipman

  9. Marion from Chipman to Hanover

  10. Morris from Mack to north end

  11. North St over Corlett Creek

  12. Orchard from Marion to north end

     

    Project is scheduled to be awarded to Highway Maintenance at the April 5 city council meeting.  Work will begin around July 6, 2021 and be completed by September 10, 2021.

     

2021 Street Patch Program

Contract has been awarded to Smith Sand and Gravel.  Project will start around July 6, 2021.

 

2021 Sidewalk Program

Project is under design phase.  Project will be advertised for bids at the end of April.  Work will begin on or around July 6, 2021.

 

2021 City Hall Retaining Wall Project

Project is scheduled to be awarded to Gordon Construction Services at the April 5 city council meeting.  Base bid includes retaining wall, railing, turf restoration, and sidewalk reconstruction along the upper and lower portions of the retaining wall.  Sidewalk south of the retaining wall including in the alternate bid will be reconstructed at a later date.  Geotechnical work will begin June 2021.  DPW staff will do tree work and lighting/electrical work prior to wall construction.  Wall reconstruction is scheduled to begin July 2021 and be completed early September 2021.

 

Maple Avenue Project

  1. Maple Avenue from Corunna to north end: Work scope includes street reconstruction and water main replacement from a 4 inch main to a 6 inch main.  Project under design phase.  DPW scheduled to replace water main late Summer/early Fall 2021.  Street construction will begin Spring 2022.

     

Future Projects (2023)

Projects planned for water main construction:

  1. Clyde Street from Walnut to Shiawassee: Work scope includes water main replacement. Project under design phase.

  2. Huron Street from Huggins to east end: Work scope includes water main replacement. Project under design phase.

  3. Lynn St from Howell to west end: Work scope includes water main replacement. Project under design phase.

  4. Milwaukee Street from S Lyon to S Cedar: Work scope includes water main replacement. Project under design phase.