Road reconstruction work is progressing according to schedule. Recent rains have slowed work but has not affected scheduling. The contractor plans to continue removals and placing new aggregate base until its completion sometime mid-week of July 17. The Oliver Street/Washington Street intersection will be closed for up to a three week period beginning July 14 for its construction. A signed detour route will be in affect while the intersection is closed to traffic. Concrete work is scheduled to begin on or about July 19; that includes curb and gutter, sidewalk, and driveway approaches. All concrete work should be completed approximately July 28. New asphalt pavement will then begin soon thereafter. Completion date for all work is August 24, 2017 and the contractor is on schedule to meet that requirement.