Seventh Street is scheduled for asphalt work the week of October 7, 2019.  Schedule is for first asphalt course on Monday.  Contractor will raise sewer structure covers Tuesday.  Then, final asphalt course on Wednesday.  All work is weather dependent and could be extended to the end of the week.