Ryan Street is scheduled for asphalt work the week of October 7, 2019.  Schedule is for first asphalt course on Monday.  Contractor will raise sewer structure covers Tuesday.  Then final asphalt course on Wednesday.  For protection of the workers and motorists, the intersection of Chipman/Ryan will be closed these three days as well to complete its pavement restoration.  A signed detour will be in effect to move Chipman Street traffic around the worksite.  The detour route will be Stewart/Martin/Milwaukee Streets.  All work is weather dependent and could be extended to the end of the week.