Water main replacement is continuing through November 8, due to issues with the water main.  Storm sewer will be worked on through November 14, due to the delay caused by the storm sewer work.  Road excavation, aggregate base, curb & gutter and sidewalk work should be completed by November 13.  Asphalt paving will take place November 20-22.  Restoration and cleanup will occur November 27-30.  Keep in mind this is subject to change based on weather.