On Monday, November 23, DPW crews finished N4 and moved into N5.  On Tuesday, November 24 they will be working on trunklines (M21, M71, and M52).  Once trunklines are completed they will move back into N5.

Leaf crews follow this section order: N1, S1, S2, N2, N3, S3, S4, N4, N5, S5, S6, N6, N7, S7, S8, N8.