PROJECT STATUS REPORT

DPW Water Main Projects
1.     Washington Street from Stewart Street to Milwaukee Street: Water main work is complete.
2.     Seventh Street from Oliver Street to King Street & King Street from Seventh Street to Fifth Street:  Water main and services are complete.  Tie-in at King and Fifth is yet to be completed.  It is scheduled for the week of June 24th.

2019 Street Program-Contract 1
1.     Palmer Avenue from Gute Street to Prindle Street:  Street work is completed.  Open to traffic date was May 13th.
2.     W Williams Street from Shiawassee Street to Washington Street:  Storm sewer from Pine to Adams and the outlet to the river is complete.  Existing road has been pulverized and existing concrete has been removed.  Storm sewer work will continue in the street working from Adams east to Washington.  Road removal and limestone placement will follow behind storm sewer work.  Concrete placement and asphalt paving to follow.  Project is behind original schedule due to both weather and field conditions. Expected completion date is revised to July 26, 2019.

2019 Street Program-Contract 2
1.     Abrey Avenue from Melinda Street to Allendale Avenue:  Project scheduled to start on/after July 8th.  Open to traffic date is August 30th.  Consumers Energy has completed their gas main and restoration work.
2.     Allendale Avenue from Gould Street to east city limits:  Project scheduled to start on/after July 8th.  Open to traffic date is August 30th.  Consumers Energy has completed their gas main and restoration work.
3.     Monroe Street from McMillan to east city limits:  Project scheduled to start on/after July 8th.  Open to traffic date is August 30th.
4.     North Street from west city limits to N Chipman Street:  Project scheduled to start on/after July 8th.  Open to traffic date is August 30th.

2019 Street Program-Contract 3
1.     Ryan Street from S Chipman Street to Cedar Street:  Project scheduled to start on/after July 8th.  Open to traffic date is September 20th.
2.     Seventh Street from W Oliver Street to W King Street:  Project scheduled to start on/after August 5th.  Open to traffic date is September 20th.

MDOT Local Safety Grant Project
1.     S Washington Street from Gute Street to Corunna Avenue:  Project started June 11, 2019. Road is pulverized and storm sewer work is in progress. Project is on schedule with expected open to traffic date as September 13th. Work scope includes water main replacement under Huron & Eastern Railroad, pavement reconstruction, storm sewer improvements, road realignment, permanent pavement markings and signing, bike lanes, and all-way STOP controls at intersection of Stewart/ Washington.

2019 Street Patch Program
Various locations around the city:  Contract awarded to L & L Excavating of Reese.  Project scheduled to start on/after July 8th. 

2019 Sidewalk Program
The follow areas are the work area:
1.     Section of the city enclosed by N Washington St, E King St, N Dewey St, and E Oliver St.
2.     Residential complaint areas.
3.     Road Construction follow up areas on S Chipman St, W Stewart St, S Chestnut St, N Chipman St, Olmstead St, and Hanover St (if budget allows)
Project scheduled to start on/after July 8th.  Completion date is October 25th.

2019 Sanitary and Storm Sewer Rehabilitation Project
Sewer cleaning and televising work 90% complete. Contractor and City Consultant will evaluate televising information, identify specific repair locations and type, then order materials. Contractor will focus on high priority work sites and complete them in advance of street construction. Remaining sewer rehabilitation work is rescheduled to commence for June 24, 2019.  Argus Press and city website has been notified of revised schedule.

2020 Projects
Projects planned for street construction:
1.     S. Cedar Street from South Street to Hampton Street. Work scope includes water main replacement, select storm sewer replacement, and pavement rehabilitation. Project under design phase.
2.     Summit Street from Abbott to Rubelman Drive. Work scope includes water main replacement, pavement rehabilitation, and storm sewer improvements. Project designed and ready for contractor bids.
3.     North Street from Hickory Street to Gould Street. Work scope includes water main replacement, full street reconstruction and storm sewer replacement.  Road and storm sewer design about 90% complete. Water main design will be performed by Consultant.
4.     Clark Street from Oliver Street to King Street. Work scope includes water main replacement, pavement rehabilitation, and storm sewer improvements.  Road and storm sewer design about 70% complete.  Water main design will be performed by Consultant.