2018 Street Program:
1.  W. Stewart Street, Chestnut Street to Chipman Street: Isolated curb and gutter repairs completed.  Structure covers adjusted and road is ready for last course of asphalt (scheduled for July 2, 2018).  
2.  S. Chipman Street, South Street to Stewart Street: Completed work includes watermain, storm sewer, curb and gutter, sidewalk, and first course of asphalt.  Contractor now working on raising structures for final course of asphalt (scheduled for July 2 and 3, 2018).  
Project completion delayed to July 3, 2018.

Oliver Street, Phase 2, from Oak Street to Gould Street:  Old pavement removed and driveways made accessible.  Watermain in place and accepted for connection to city potable water system.  for July, contractor plan to complete water main, storm sewer, road excavation and new base.  Project is scheduled for October 10, 2018 completion.

Industrial Park Connector Project:
1.  McMillan Avenue from Monroe Street south: New storm sewer construction is about 40% complete.  For July, contractor plans to complete new road construction along McMillan Avenue, then begin work on Monroe Street.
2.  Monroe Street from Gould Street to McMillan Avenue: Street will be closed to traffic beginning July 21, 2018.  Contractor is to begin storm sewer work on July 21, then begin constructing new road soon thereafter.  Road will be closed to through traffic until August 25, 2018.  Truck traffic is detoured by signed route along M-71/Legion Road/Cornell Road/Aiken Road/Industrial Drive until road is reopened to traffic.
3.  Gould Street from Monroe Street to M-72: No work planned until August.
Project is on schedule for October 20, 2018 completion.

2018 Street Program - Contract 1:
1.  Olmstead Street from West Street to Chipman Street: Water main in place and accepted for connection to city potable water system.  For July, contractor plans to complete water main, storm sewer, road excavation and pavement work.
2.  Harding Avenue from Chipman Street to Havover Street: Water main in place and accepted for connection to city potable water system.  For July, contractor plans to complete water main, storm sewer, road excavation and pavement work.
3.  Hanover Street from Harding Avenue to north end - for July, contractor plans to begin watermain work.
Project is on schedule for August 31, 2018 completion.

2018 Street Program - Contract 2:
1.  Howard Street from Washington Street to Park Street: Contractor completed storm sewer, road excavation and base work.  For July, contractor plants to complete the curb and gutter, sidewalk and asphalt pavement.  Restoration work will follow soon thereafter.
2.  Stewart Street from Cedar Street to Shiawassee Street: Contractor began locating utilities for upcoming construction work.  For July, contractor plans to complete water main, storm sewer and road work through base.
Project is on schedule for August 31, 2018 completion.