News

View Article

May
16

The Olmstead St., Harding Ave., and Hanover St. road resurfacing projects are scheduled to begin on May 21, 2018.  Water main replacement is scheduled to begin the week of May 21, 2018 and continue through the end of June.  Storm sewer and road work will follow as the areas are cleared from the water main work.  The roads will be closed to through traffic.  Local traffic will be maintained.  The projects are scheduled for completion on or before August 31, 2018.  Any questions or comments may be submitted to the City of Owosso DPW office, by telephone, at 989-725-0550.