News

View Article

May
01

The E. Oliver St., from Oak St. to Gould St., reconstruction project is scheduled to begin May 14, 2018.  Road pulverizing and some pavement removal will be done in advance of water main replacement.  Water main replacement should begin about May 25, 2018 and continue through the end of June, 2018.  Storm sewer and road work will follow as the area is cleared from the water main work.  Through traffic is detoured by a signed route using Hickory St., Main St. and Gould St.  Local traffic will be maintained.  All business is open during the construction period.  The road is scheduled to be reopened for regular use on August 31, 2018.  The entire project is scheduled for completion on or before October 10, 2018.  Any questions or comments may be submitted to the City of Owosso DPW office, by telephone, at 989-725-0550.