News

View Article

Apr
13

The S. Chipman Street, from South Street to Stewart Street, resurfacing project began April 2, 2018.  Water main replacement is in progress and on schedule.  Storm sewer and road work will follow as the area is cleared from the water main work.  Through traffic is detoured by a signed route that uses Cedar Street, from South Street to Stewart Street.  Local traffic is maintained.  All businesses are open during the construction period.  The entire project is scheduled for completion on or before June 29, 2018.  Any questions or comments may be submitted to the City of Owosso DPW office, by telephone, at 989-725-0550.