The S. Chipman Street, from South Street to Stewart Street, resurfacing project is progressing according to schedule.  The new water main is in place, house services are transferred, and final work is nearly completed.  Storm sewer work is 90% complete.  Road excavation and new pavement work is scheduled to begin about June 11, 2018.  Through traffic is detoured by a signed route that uses Cedar Street, from South Street to Stewart Street.  Local traffic is maintained.  All businesses are open during the construction period.  The entire project is scheduled for completion on or before June 29, 2018.  Any questions or comments may be submitted to the City of Owosso Engineering office, by telephone, at 989-725-0550.