Construction work is progressing according to schedule.  All concrete work including curb and gutter, sidewalk, driveway approaches should be complete the week of August 7, 2017.  The first course of asphalt is scheduled for August 10, 2017.  Final asphalt course and site restoration work will follow soon thereafter to meet the completion date of August 24, 2017.